PROJECTS INFORMATION and Status

GENERAL:
There were several preparatory works have been completed during developing projects. Some of the key works have been listed for the references as below:

  • The Power Purchase Agreement for the two projects has been signed with NEA.
  • Generation Licenses for both the projects has been received from the Ministry of Energy for a period of 35 years.
  • Registration in the Department of Industry (DoI) for both the projects has been completed.
  • Approval for Tree Cutting has been obtained from the GoN, Department of Forest
  • Construction of five pre-fabricated houses at Thambuchet and two pre-fabricated houses at Tetanchet has been completed.
  • Construction of Camps and Offices for Project Staffs at Thambuchet has been completed
  • Construction of dedicated 11 kV transmission line (9 km) from Chilime Power Plant to the project site Thambuchet has been completed.
  • Extension and strengthening of 11 kV line (10 km) for construction power lines up to Tilocheheadworks and to construction-adits and surge tank has been completed.
  • Contract Agreement for the Construction of Lot 2 Civil Works of Sanjen (Upper) Hydroelectric Project was signed with M/S ECI BGCCPL J/V
  • Contract Agreement for the Construction of Lot 2 Civil Works of Sanjen Hydroelectric Project has been signed with M/S SEW TUNDI J/V
  • Contract Agreement for Lot 3 Electromechanical Works of both Sanjen (Upper) and Sanjen Hydroelectric Projects with the same Contractor with different packages has been with signed M/S Dongfang Electric International, China.
  • Contract Agreement for Lot 4 Hydromechanical Works of Sanjen (Upper) and Sanjen Hydroelectric Projects with the same Contractor with different packages has been signed with M/S Nepal Hydro & Electric Limited, Nepal.
  • Contract Agreement for Lot 5 Transmission Lines Works for bothSanjen (Upper) and Sanjen Hydroelectric Projects in a single package has been signed with M/S Mudabhary and Joshi Pvt. Co. Limited.

  • project main works

    Lot1 Infrastructure Works
    All the infrastructural works including access road to project site and approach to the main working fronts, the camp facilities for the Employer, construction power lines with different packages have been implemented under this packages. Almost all of the works under this packages have been completed.


    Lot 2: Civil Works-SUHEP
    Almost all the headwork structure has been completed and interfacing works with Lot 4 (Hydro-Mechanical) is undergoing and balancing pond construction work is underway with 20 percent completion status. All tunnel works including Head Race Tunnel (HRT), Penstock Tunnel etc. excavation and lining work is completed and tunnel grouting work is underway. Penstock installation work is undergoing. Powerhouse substructure work is in progress and 50% of the Powerhouse back slope stabilization work is completed. Overall 73% of the physical progress has been achieved.

    Lot2:Civil Works-SHEP
    Contract Agreement for the Construction of Lot 2 Civil Works of Sanjen Hydroelectric Project was signed with M/S SEW – TUNDI J/V. Major activities under this contract are going as follows: The headwork structure work is in the final stage: Half portion of the weir is completed and the other second half is under construction, construction of desander is completed, peaking pond and forebay is almost completed and interfacing works with Lot 4 (Hydro-Mechanical) is undergoing. Head Race Tunnel (HRT) is underway: 2658.2m excavation work is completed out of 3641.9m. Surge-Shaft: 47m out of 51m height Surge shaft excavation work has been completed. Penstock Tunnel: 644m excavation work is completed out of 939m. Adit Tunnel: All adit tunnels work has been completed. Powerhouse: 45 % of civil works of Powerhouse is completed. Overall 67% of the physical progress has been achieved.

    Lot 3: Electromechanical Works-SUHEP
    Contract Agreement for Lot 3 Electromechanical Works of Sanjen (Upper) and Sanjen Hydroelectric Projects was signed with M/S Dongfang Electric International, China. Major activities undergoing in this contract are: For SUHEP Under this lot Design, Fabrication, Factory Inspection & delivery works are undergoing. In Design part 89% of the work has been completed In manufacturing part 75% of the work has been completed that includes manufacture of turbine, generator, transformer etc. In delivery part delivery part 34% of the work has been completed. Overall 61.2% of the physical progress has been achieved.

    Lot 3: Electromechanical Works -SHEP:

    Under this lot Design, Fabrication, Factory Inspection & delivery works are undergoing. In Design part 78% of the work has been completed In manufacturing part 78% of the work has been completed that includes manufacture of turbine, generator, transformer etc. In delivery part delivery part 43% of the work has been completed. Overall 58.5% of the physical progress has been achieved.

    Lot 4: Hydro mechanical Works-SUHEP Contract Agreement for Lot 4 – Hydromechanical Works of Sanjen (Upper) and Sanjen Hydroelectric Projects was signed with M/S Nepal Hydro & Electric Limited, Nepal. Major project progress status under this contract are: For SUHEP Under this lot Design, Fabrication, Factory Inspection & delivery works are undergoing. In Design part 99% of the work has been completed. In manufacturing part 89% of the work has been completed that includes manufacture of penstock pipe, gates, stop logs etc. In delivery part 58% of the work has been completed. Overall 68% of the physical progress has been achieved.

    Lot 4: Hydro mechanical Works-SHEP
    Under this lot Design, Fabrication, Factory Inspection & delivery works are undergoing. In Design part 96% of the work has been completed In manufacturing part 71% of the work has been completed that includes manufacture of penstock pipe, gates, stoplogs etc. In delivery part 42% of the work has been completed. In Installation 6% of the work has been completed. Overall 54% of the physical progress has been achieved.


    Lot 5: Transmission Lines Works :
    The transmission lines for both projects has been considered in single packages. It consist of around 6 km long 132 KV single circuit transmission line from SUHEP powerhouse to Chilime Hub and also 132 KV double circuit line from SHEP powerhouse will be connected to the same line uptoChilime Hub. For this packages contract has been already concluded. Now, the detail survey work, soil investigation has been completed and design related work is ongoing.